Cape Town wants toll road report
Ron Paschke, for the council, said Sanral had been evasive about why the city was not provided with this information.
Sanral had, however, not denied that the council was given the wrong report in the record of documents that were handed over.
He was presenting argument for an urgent interdict preventing Sanral from going ahead with the N1/N2 Winelands Toll Highway Project until a court has reviewed the legality of the project.
The council wanted a court order forcing Sanral to provide certain documents it had requested regarding the decision-making process, to assist it in the review which was pending in the same court.
It was of the view that the transport minister at the time, Jeff Radebe, decided to approve the project without knowing the full costs involved, a decision which it called "irrational".
Document dispute
Judge Ashley Binns-Ward said he was in possession of an affidavit from the minister which stated that the city had received all the necessary documents.
He said it could thus be a possibility that the minister may not have been shown or have been aware of all the documents.
Paschke agreed, saying: "We know there's a mistake [between the reports we have and the reports Sanral has]. We know there are documents which the minister has not seen."
In addition, the council believed there was evidence to suggest the environmental minister at the time authorised the project based only on its environmental impact, not the socio-economic impact on the surrounding communities.
The council insisted that the courts were the only avenue it could pursue for these documents, which it believed it was entitled to in terms of the Constitution.
Deceit denied
Chris Loxton SC, for Sanral, argued that the council was approaching the matter in an "upside down" manner. He said the the council was against tolling as a method of funding upgrades to certain roads, as a matter of principle.
"We can't tell the environmental authorities to consider the socio-economic impacts, when one first has to get authority to build the road before we can work out how to fund it," Loxton said.
He said the primary objective was to upgrade the road.
The steps to be followed were to start concluding a concessionaire contract, calculate the total costs involved and then see if it was feasible to collect the funding required through tolls alone or through co-contributions.
Loxton said Sanral was not being deceitful as to cost breakdowns of the project. It was simply "impossible to know" at this stage, he said.
He criticised the council for taking three years to institute legal proceedings.
The proposed concession route along the N1 extends from west of the R300 interchange through to Sandhills. The N2 portion of the proposed toll road concession extends from west of the R300 to Bot River.
According to a diagram on Sanral's website, 106km of the N1 and 70km of the N2 would be tolled should the project go ahead.
Sanral will continue its arguments on Friday (17 May).
Source: I-Net Bridge
For more than two decades, I-Net Bridge has been one of South Africa’s preferred electronic providers of innovative solutions, data of the highest calibre, reliable platforms and excellent supporting systems. Our products include workstations, web applications and data feeds packaged with in-depth news and powerful analytical tools empowering clients to make meaningful decisions.
We pride ourselves on our wide variety of in-house skills, encompassing multiple platforms and applications. These skills enable us to not only function as a first class facility, but also design, implement and support all our client needs at a level that confirms I-Net Bridge a leader in its field.
Go to: http://www.inet.co.za