Eskom implements Stage 4 load shedding
“Regretfully, Eskom has been forced to implement Stage 4 load shedding at 07:20 [today] after Majuba Unit 5 and Tutuka Unit 4 tripped,” the power utility said in tweet on Tuesday morning.
Eskom resumed load shedding on Sunday afternoon following additional generation unit losses and the delayed return to service of generators.
On Sunday, the loss of four additional generation units at Matla, Tutuka, Duvha and Arnot power stations, exacerbated by the delay in units returning to service at Camden, Matla, Grootvlei and Tutuka power stations, necessitated the implementation of Stage 2 load shedding.
Since Friday afternoon, a generation unit each at Camden, Komati and Arnot power stations returned to service.
Source: SAnews.gov.za
SAnews.gov.za is a South African government news service, published by the Government Communication and Information System (GCIS). SAnews.gov.za (formerly BuaNews) was established to provide quick and easy access to articles and feature stories aimed at keeping the public informed about the implementation of government mandates.
Go to: http://www.sanews.gov.za