South Africa’s R19.7bn Mokolo and Crocodile Water Augmentation Project (MCWAP-2A) faces a crucial progress check as Water and Sanitation Minister Pemmy Majodina and Deputy Minister David Mahlobo inspect construction sites in Limpopo on Tuesday, 20 October 2026.
The delegation will assess pipeline-laying works, examine implementation challenges and inspect key abstraction infrastructure near Thabazimbi to evaluate progress and determine how the project will contribute to the district’s long-term water security.
The inspections come as government seeks to keep the project on track to improve water security and support economic growth. Its approximately 140km pipeline will transport raw water from the Crocodile River to Lephalale and surrounding areas, providing a more reliable supply for major economic users and communities.
The project is also expected to bolster bulk water infrastructure in the Waterberg District Municipality, helping meet the needs of communities dependent on sustainable water supplies.
MCWAP-2A includes an abstraction weir, water-transfer pipeline, pump stations, and associated ancillary infrastructure, a river management system and an operational control centre.
Securing economic growth
Once completed, MCWAP-2A will provide an additional bulk raw water source for major economic users, including Eskom’s Medupi and Matimba power stations and Exxaro’s Grootegeluk mine, as well as commercial and industrial users.
“The purpose of the oversight visit is to assess progress on this strategic water infrastructure project, which is critical to strengthening long-term water security and supporting economic and industrial activity in the district,” the Department of Water and Sanitation said.
The project is being implemented by the Trans-Caledon Tunnel Authority (TCTA), the department’s entity responsible for financing and implementing bulk raw water infrastructure.