Kusile's unit 2 attains its commercial operation status

Unit 2 at Kusile Power Station in eMalahleni, Mpumalanga, has been brought into full commercial operation status to further stabilise the power system.
Kusile Power Station
Kusile Power Station

“This morning it was officially handed over to the generation business of Eskom from the group's capital projects division, which was responsible for the building,” power utility said in a statement.

This means the unit officially moves to be part of Eskom’s generation fleet, contributing up to 800MW to the South African power grid, after undergoing testing and optimisation over the past 16 months.

“The commercial operation of unit 2 is a major milestone that signifies the progress being made by Eskom towards the completion of the Kusile Build Project, on which lie the nation’s best hopes to bring stability and ensure the security of electricity supply to power the South African economy,” said Bheki Nxumalo, Eskom’s group executive for capital projects.

Kusile, along with Medupi power station, are Eskom's two coal-fired new build projects. The construction of both has been plagued with major design flaws, and running into billions of dollars over budget and way over deadline.

Unit 2 is the second unit at Kusile to enter commercial operation, with unit 1 having attained the status in 2017.

According to Eskom, the construction, testing and optimisation activities on the remaining four units, some of which are currently providing intermittent power to support the grid, is progressing well.

Eskom said the commercial operation status ensures technical compliance to statutory, safety and legal requirements.

Kusile is the first power station in South Africa and Africa to use wet flue gas desulphurisation (WFGD) technology. WFGD is the current state-of-the-art technology used to remove oxides of sulphur (SOx), such as sulphur dioxide, from exhaust flue gases in power plants that burn coal or oil.

“Eskom is fitting WFGD to the Kusile plant as an atmospheric emission abatement technology, in line with current international practise, to ensure compliance with air quality standards,” the utility said.

Source: SAnews.gov.za

SAnews.gov.za is a South African government news service, published by the Government Communication and Information System (GCIS). SAnews.gov.za (formerly BuaNews) was established to provide quick and easy access to articles and feature stories aimed at keeping the public informed about the implementation of government mandates.