Gutted by riots, rebuild of Greater Edendale Mall now underway

The 32,000m2 Greater Edendale Mall located in Pietermaritzburg would have celebrated its ten-year birthday in November 2021 but was completely gutted in the week of unrest that took place in July. Exemplar REITail has begun the rebuild process which is expected to take approximately 18 months.
Fire damage at Greater Edendale Mall. Image supplied
Fire damage at Greater Edendale Mall. Image supplied

Site establishment and demolition works began in the first week of February and are expected to take approximately eight weeks, whereafter contractors will be appointed to commence construction.

Fire damage at Greater Edendale Mall. Image supplied
Fire damage at Greater Edendale Mall. Image supplied

According to Exemplar, the latest trends will be incorporated into the layout, lighting and tenant mix, including natural lighting, full height glass shop fronts and high ceilings. Rooftop PV systems and efficient utility management will also be core to the development.

CEO of Exemplar, Jason McCormick, is excited to bring retail back to the community: “The damage to the mall and the impact it had on the micro-economy of the community was devastating to witness. The riots had a disastrous impact on small businesses. Many of our local tenants have closed and won’t be reopening their doors. But this has provided us with the unexpected opportunity of finding new talent while providing a refreshed tenant mix that speaks directly to the immediate needs of the community.”

Greater Edendale Mall. Image supplied
Greater Edendale Mall. Image supplied

Exemplar’s assets in KZN were extensively impacted in the riots. Greater Edendale Mall, Mandeni Mall and Theku Plaza all suffered structural and fire damage. Both Mandeni Mall and Theku Plaza were repaired and trading by December last year.