Building big: Inside Sandton’s landmark Olympus development

South Africa’s construction industry is reaching new heights with Olympus, an ambitious near-R2bn development set to transform Sandton’s skyline.
Source: Supplied. A rendered view of Olympus, Barrow Construction’s landmark two-tower residential development, transforming Sandton’s skyline through scale, design and innovation.
Source: Supplied. A rendered view of Olympus, Barrow Construction’s landmark two-tower residential development, transforming Sandton’s skyline through scale, design and innovation.

Undertaken by Barrow Construction, the project is the country’s largest single-phase development of its kind, bringing two residential towers of 24 and 28 floors to life within an ambitious 22-month construction programme.

With construction costs starting at R840m and expected to exceed R1bn, Olympus is more than a landmark luxury address. It is a test of the scale, speed and capabilities of South African construction.

Developed by Tricolt and Growthpoint, Olympus is a luxury residential address with a public heart. At street level, visitors will walk up a stair into the lobby of Maison Marble, the boutique hotel. To the left is Pantry, a double storey space open to anyone, reached by a spiral stair. From its upper level, visitors can look across to the lounges and breakfast areas of the hotel above.

The hotel sits on top of the Pantry level. Higher up, a restaurant, Jellyfish by Marble group, will occupy the 18th floor inside the cloud-shaped structure that crowns the lower levels.

Above the podium, the residential towers step back and rise in an oscillating form, with feature Led lighting along the slab edges, designed to make a statement. The podium itself will carry 5,000m² of greenery, with creepers cascading down the building.

Shaneel Singh from Barrow puts the height in perspective: "We are going to be sitting 42m higher than Discovery.”

Overcoming construction challenges

The start of the project was slowed due to the erratic nature of Sandton rock. In the north western corner, it measured around 460MPa, against 30MPa for structural concrete. It could not be blasted, so the team drilled, fractured and removed it. The painstaking drilling took two months and left the project 33 working days behind programme.

Through weekend shifts and engineering changes, Tower 1 is back on programme and Tower 2 is closing in. The expected completion is around 17 May 2028. Olympus is targeting five Green Star stars, with fly ash concrete, recycled cladding and performance glazing. A bespoke perforated brick from Cape Town and imported Italian tiles will give it a luxury finish.

Singh attributes the project's success thus far to the Barrow Construction team and their subcontractors. On risk, he is candid: “I’m worried that we’re not worried.” The team now hunts for the next risk, managing it six to seven weeks at a time. “Olympus is a flagship in Sandton. It’s going to kickstart Sandton all over again.”